1. Project Overview

A leading multinational pharmaceutical company embarked on a strategic initiative to establish a state-of-the-art research laboratory in [Location – e.g., Singapore, Boston, or Shanghai]. The facility was designed to support early-stage drug discovery, formulation development, and potency analysis for novel oncology and gene therapy products.

To meet stringent regulatory requirements (EU GMP, FDA cGMP, and ISO 14644), the company required a fully integrated cleanroom equipment solution capable of achieving ISO Class 5 to ISO Class 7 environments, with specialized containment for highly potent active pharmaceutical ingredients (HPAPIs).

2. Client Requirements

  • Strict Contamination Control: Prevention of cross-contamination between different research modules (e.g., cell culture, virology, and chemical synthesis).

  • High Containment: Negative pressure suites with HEPA/ULPA filtration and pass-through systems for handling OEB Level 4 and 5 compounds.

  • Precision Environmental Control: Temperature stability at 21±1∘�, relative humidity 45±5%, and room pressure cascade from clean to dirty corridors.

  • Modular Scalability: Ability to expand or reconfigure lab modules without major renovation.

  • Data Integrity & Monitoring: Continuous monitoring of particle counts, differential pressure, and airflow velocity.

3. Cleanroom Equipment Engineering Solution

Our engineering team delivered a turnkey cleanroom equipment package comprising:

A. HVAC and Filtration Systems

  • AHUs with Energy Recovery: Redundant air handling units with VFD-controlled fans.

  • HEPA Filter Ceiling Modules: Terminal HEPA filters (99.997% @ 0.3 µm) with leak-tested housings.

  • Unidirectional Airflow Units (UDAFs): Installed over biosafety cabinets and filling stations to maintain ISO Class 5 zones.

B. Modular Cleanroom Architecture

  • Hardwall Modular Panels: Non-porous, chemical-resistant polyurethane or mineral core panels with rounded cove corners for easy cleaning.

  • Interlocking Air-Tight Doors: With magnetic gaskets and vision panels.

  • Pass-Through Chambers: Interlocked, HEPA-filtered pass-boxes for safe material transfer.

C. Containment and Safety Equipment

  • Biosafety Cabinets (BSC Class II Type B2): 100% exhaust units connected to dedicated containment ducts.

  • Powder Containment Hoods: Downflow booths (DFB) for weighing and dispensing HPAPIs.

  • Bag-In/Bag-Out (BIBO) Filter Housings: For safe filter replacement without operator exposure.

D. Monitoring and Control System (BMS/EMS)

  • Real-time sensors for particle count, differential pressure, temp/RH.

  • Alarm and alert integration with the client’s central SCADA system.

  • Data logging compliant with 21 CFR Part 11.

4. Key Engineering Challenges & Solutions

 
 
Challenge Solution
Achieving ≤ 0.1 Pa pressure cascade between 20 rooms Motorized dampers with closed-loop PID control
Minimizing vibration near sensitive analytical balances Isolated equipment platforms and anti-vibration mounts
Maintaining cleanliness during phased construction Portable mini-environment units and strict gowning protocols for installers
Validating airflow patterns Smoke studies and computational fluid dynamics (CFD) simulations pre-installation

5. Validation & Compliance

All cleanroom equipment was installed and qualified according to V-model approach:

  • DQ (Design Qualification): Verified ISO class, material compatibility, and airflow simulations.

  • IQ (Installation Qualification): Verified utility connections, filter integrity, and component certification.

  • OQ (Operational Qualification): Tested airflow velocity, pressure cascade, particle counts (non-viable), and alarm functionality.

  • PQ (Performance Qualification): Dynamic testing under simulated operational conditions, including aseptic media fills.

Result: The facility passed regulatory inspection with zero major observations, and achieved ISO 14644-1 Class 5 (at rest/in operation) for critical zones.

6. Project Outcome

  • Completion Time: 14 months (on schedule)

  • Cleanroom Area: 2,800 m² (including 12 modular labs and 4 support zones)

  • Energy Efficiency: 28% reduction in HVAC energy consumption compared to conventional designs

  • Operational Readiness: Successful commissioning of 8 HPAPI containment suites

The client now operates a flexible, safe, and compliant research laboratory, accelerating its oncology pipeline with minimized cross-contamination risk.

7. Conclusion

This case study demonstrates that for multinational pharmaceutical R&D projects, engineered cleanroom equipment—not just construction—is the cornerstone of regulatory compliance and operational excellence. By integrating modular hardwall systems, precision HVAC, and real-time monitoring, the project met all scientific, safety, and scalability requirements.

←
1

電晶體設施中潔淨室安裝的關鍵考慮因素是什麼?

正確的規劃對於在高科技行業成功安裝潔淨室至關重要。 工程師必須評估氣流動力學和壓差,以在潔淨室實驗室環境中保持ISO標準。 集成可靠的潔淨室聯鎖系統可確保人員進入時的壓力穩定性,防止電晶體工廠或生物製藥套房等敏感製造區的污染風險。

2

潔淨室聯鎖門如何增强污染控制協定?

潔淨室聯鎖門可防止兩扇門同時打開,保持壓力級聯。 這種機制對於任何需要嚴格隔離的潔淨室實驗室都至關重要。 潔淨室聯鎖門的具體設計最大限度地减少了轉移過程中顆粒的進入,確保符合航空航太或醫療器械製造法規,同時不影響運營效率。

留言

我們很樂意收到你的來信。 給我們發消息,我們會儘快回復
X